Fixing the roof
and cresting
Table of Contents
Click on thumbnails below to see larger pictures of the
roof.
 |
August 2003: When we
bought the house, the main stairway and upstairs hallway had hand-stenciled
red paint. At one time this must have looked great, but many years of
plaster repair and other problems left these areas dingy. We decided to
install stained glass windows in the stairway ceiling to let outside light
shine down the stairway. |

 |
July 2004: One of the first steps
was to build a skylight on top of the house. Because this skylight cannot be
seen from the street, we didn't need to ask for approval from the local
Landmark Advisory Commission. I used a 3/8-inch Plexiglas sheet to let light flow into
the attic. |

 |
August 2004
Top: This view shows the bottom of the skylight as
seen when you look through the attic at night. Bill Cutler painted the 2x4s
and other wood members white so they would reflect more light down onto the
stained glass windows below.
Bottom: I've cut a 4 by 4-foot hole in the
second story ceiling. This will just fit the two antique stained glass
windows we bought on eBay. |

 |
August 2004, Top: Looking down on the stained glass
windows from the attic. The windows we bought were made around 1880 and
spent most of their life in an English home. Barb and I couldn't agree on
which windows to purchase, so when we finally found a pair of windows we
both liked, we put in quite a high bid. We hoped other people wouldn't bid
as high -- and we were wrong, so this became a very expensive project. Once
the windows arrived, we had extra metal strapping added on their back side
so they should be able to hang horizontally without sagging. You can see
these additional metal straps running down the center of the window and
through the fleur-de-lis pattern.
Bottom: We installed mirrors to guide light
onto the stained glass. Below the mirrors, I installed two banks of
florescent lights and wired them into the hallway light switch. Now whenever
we turn on the hallway light, the stained glass windows light up
beautifully. Also, if you look carefully, you can see I installed a
Plexiglas sheet directly above the stained glass windows. I sealed the area
from air leakage with spray foam and double-sided foam tape. All this effort
created a trapped dead air space to resist heat flow, and it keeps the
stained glass windows clean. |

 |
December 2004: The finished project as seen from the
stairway. These pictures really don't do the project justice -- the depth of
the stained glass is wonderful when light shines through it. |
 |
It took a lot longer to reinstall the cresting than it
took to remove. I bought stainless steel bolts and washers, so the new
cresting won't be stained with rust from the fasteners. |
 |
The cresting returned from powder coating in October
2003,
and it gleamed. It looks much better than this photograph shows. We had each
piece sandblasted and coated with two layers of white paint. |
 |
This is a same area Dave Helton and I
built that had all the dry rot. I'm particularly happy with
the "stealth" vents -- they blend in so well with the rest of the 50-year
shingles that they almost disappear. Can you spot them? |
 |
The back of the house ... all
buttoned up. |
 |
A close-up view of the square nails used
in the 1880's to hold down the metal roofing. |
 |
A truck with a long conveyor belt
delivered all the roofing to the flat part of the roof prior to removing the
old roofing. |
 |
Bruce Taylor of Do It Again Decor contracted to do the
roofing. You see him here in the midst of tearing off the old roof. He did a
super job -- highly recommended. |
 |
The old roofing comes off while the new
roofing sits on the flat walkway. |
 |
More roof removal. |
 |
With the old roof removed, some areas
were ready for plywood. |
 |
After tearing off the roofing, other
areas -- such as this east-side gutter -- revealed significant amounts of dry rot. |
 |
All the old roofing is now off, and we
have covered the roof with tarps. This picture shows David Helton who helped
repair the dry rot. |
 |
The new shingles await
installation while the rest of the roof is covered with tarps. |
 |
We have removed most of the eave over the
kitchen to
expose the rot and begin building replacements. You can see the first new
replacement cedar rafter sticking out. |
 |
David Helton considers how to install
replacement cedar 2-by-6s to repair the dry rot. We had to rebuilt this
portion of the eves from scratch. |
 |
To provide healthy ventilation to the
attic, I cut holes below the walkway. Each hole will receive a 4" by 12"
white louvered vent. |
 |
Bruce Taylor is building up a waterproof valley. |
 |
Bruce replaced the metal gutter system by:
- removing and replacing any boards showing dry
rot.
- nailing a fiberglass mesh to reinforce the
gutter's valley,
- using a metal flashing so the gutter would look identical from the street
- installing a "torch-down" rubberized membrane topped with
composition roofing. Bruce welded this top layer to the fiberglass by heating it
with a gas torch.
|
 |
After several weeks at MEI Powder
Coating, the metal cresting looking absolutely super. The sandblasted and
gave each piece two coats. Unfortunately, the picture doesn't really do them
justice -- they just gleam. Now I will have to find bolts that won't rust
and spend several days reinstalling them. |
 |
Almost done! Nearly all the roofing is
gone from the walkway. Bruce Taylor was the real hero of this project--two
thumbs up for his professional ethic and approach. |
 |
When we bought the house, the cresting was rusty. It just
didn't seem like I could simply paint away the rust, so I decided to remove
all the cresting, have it sandblasted and powder coated. |
 |
I began removing bolts to separate the cresting into
movable pieces. |
 |
Pieces of cresting head down the crawl hole |
 |
Only the 2 by 4 supports remain. |
 |
The second-story roof had failed in several places before
we bought the home, so it needed to be replaced before the fall rains. |
 |
I began by checking on the historical district rules and
found we
could replace the existing composition roof with another composition roof. Very
little of the rest of the roof can be seen from the street, and the rules
allowed us to
modify things as long as the view from the street didn't change.
|
 |
I could see cedar shingles from the attic.
Both the
shingles and a layer of composition roofing needed to be removed. |
 |
You can see the flat part of the roof at
the top of this attic photo. |
 |
The walkway on the top is covered with
metal. This shows the crawl hole through the roof from the
attic. |
 |
From the crawl hole looking west. The metal cresting
is attached to pressure-treated 2 by 4s that were bolted to the roof. |
 |
Between the gutter and the walkway is a sloped roof
area. This area had a layer of composition roofing applied on top of cedar
shingles. I had both layers removed prior to installing 1/2-inch plywood
sheets covered by tar paper and 50-year shingles. |
 |
Around the entire outside edge was a built-in metal
gutter made by soldering 1-foot by 2-foot pieces of metal
together. Rebuilding the metal parts of the
roof using the original technology would have been quite expensive. |
 |
The east roof looking north along the
walkway. |
 |
The east roof from the walkway. The
patch covers were a chimney used to go through the roof. |
 |
The south roof from the walkway. |
 |
The southwest roof from the walkway. |
 |
The west roof from the walkway. Note the
downspout hole in the built-in gutter. These gutters are about two feet wide
and are covered with the same metal as the walkway. |
 |
The west roof from behind the chimney on
the south end of the walkway. |
 |
The west roof from the main walkway
showing the crawl hole and its small removable roof cap. |
 |
The northwest roof showing the upstairs bathroom vent.
The pipe through this vent was so loose we could pull it straight up. So I
ripped into the wall in the study to glue the pipe together. |
 |
The northwest roof from the north end of
the walkway. |
 |
The north roof from the walkway. |
 |
Lag bolts attached the 2 by 4s to the metal roof. This seemed like a path
for water to take into the house, so I had metal brackets made that would
allow me to attach the cresting by screwing horizontally into the edge of
the roof. |
 |
This close-up shows how the metal
roof joins the composition roof. After looking at this, I had no trouble
understanding why the roof leaked. |
 |
6th Avenue looking northwest. This photo
and the next four show the lovely views from the roof and have little to do
with the roofing project. |
 |
6th Avenue looking west. |
 |
6th Avenue looking east. |
 |
View to the southeast. |
 |
View to the southwest. |
The Allen house began life with a decorative cast iron
cresting around the top and porches. The following human interest article
explains how this cresting was removed and stored in Portland from 1966 to 1995.
The article appeared in the Albany Democrat-Herald on Saturday, May 13, 1995:

Jane Morrison, left, gathers with Roseanne and Richard
Siemens of Albany around the cast-iron cresting that blew off the house
during the 1962 Columbus Day storm.
|
Iron cresting returning to Albany roof
By Cathy Ingalls
It's like the prodigal son coming home, said Richard
Siemens as he gazed for the first time Wednesday at the boxes of cast-iron
cresting that blew off the top of his Albany house during the 1962 Columbus
Day Storm.
His wife, Roseanne Siemens, called the cast-iron
bric-a-brac the birthday candles that had decorated the top of a cake,
referring to her house at 208 Sixth Ave. S.E.
The ironwork was returned to the Siemens by
representatives of the Boxco/Milligan Foundation of Portland after it was
discovered in a Portland warehouse. The foundatino is a nonprofit
organization founded to preserve the state's historical buildings, said
foundation spokeswoman Jane Morrison.
Portland preservationists Jerry Bosco and Ben Milligan
discovered the cast iron after the 1962 storm while traipsing around Albany
looking at historic houses. One of the builder's descendants had the
cresting for sale in front of the house.
The cresting was stored with other artifacts the two
men salvaged in the Northwest over several years.
The year before Milligan died, he told the
foundation's executive director Cathy Galbraith that he wanted the cresting
returned to the Albany house if the current owners would be willing to
reinstall it.
The Siemens agreed to put it back on the home,
believed to be the first in Albany to enjoy electricity. N. H. Allen, who
built the house, generated power from a sawmill he owned. Allen ran a power
line up Baker Street from the Willamette River to the house.
Three generations of Allens lived in the house, and
later owners shared the home with 12 monkeys.
Walls in the house were covered with foam and linoleum
to muffle the noise. The house has since be restored.
The Seimens bought the house in 1987. |
The
Allen-House.Com and
RoyalHouse1873.com websites
are maintained
by
Dave and
Barbara Sullivan who live in the N. H. Allen House at 208 6th Avenue SE, Albany, Oregon. Our home phone
is 541-924-5983.
|